Staging

   

 Updated-Staging-Plan-2019.jpg  

Implementation of the LIVING CITY Master Plan will occur in stages, with specific projects progressively rolling out over a 5-10 year period.

Construction commenced on Stage 1 in June 2016 and was completed in August 2018.  Works in the Southern CBD Precinct have been undertaken concurrently with the other stages, with the new King Street Car Park completed in March 2017. 

Construction of the Waterfront Precinct is expected to commence in the second half of 2019.